Ten checks on the conditions before the price is set, whatever the standard form. A checklist, and a workbook that records every deviation from the form, your verdict and what you decided.

Herman B. Smith
CEO & Co-Founder
Updated Nov 1, 2026
A client’s contract is the standard form with changes, and the changes are where the money moves.
The checks are the same whatever the form: NEC, JCT, FIDIC, NS, AB, YSE, UAV or a bespoke set. Ten of them take an afternoon and catch most of what shows up later as a claim, a time bar or an uninsured risk.
Ten checks before you price
The contract you are offered
Scope and document hierarchy
Scope boundaries and exclusions are stated, open-ended wording is limited to what the documents describe, and an order of precedence is set.
Changes and how they are valued
A change needs a written instruction, is valued by agreed rates or a fair method, and can carry time as well as money.
Extensions of time, notices and time bars
Extensions cover client-caused delay, the notice periods are ones you can meet, and cost follows time.
Delay damages
A rate with an overall cap, triggered by dates you can influence, stated as the sole remedy for delay.
What you carry
Liability cap and indemnities
An aggregate cap in line with the contract value and your insurance, with indemnities tied to your own breach.
Ground and site risk
Relief for conditions a careful contractor could not have foreseen, with the ground investigation part of the contract.
Design responsibility and fitness for purpose
Skill and care for the design you do, with measurable performance requirements only where agreed and insurable.
Money, security and exit
Payment, retention and pay-when-paid
Stated application, certification and payment dates, retention with a release date, and no payment conditioned on the client being paid.
Bonds and guarantees
A call needs notice and a stated default, the amount steps down at completion, and expiry is a date or a certificate.
Termination and settlement
Convenience termination needs reasonable notice and pays work done, committed costs and demobilisation. Default has a cure period.
What the workbook adds. The yes/no sheet with what a good answer looks like and what to do on a no, a deviations register that records each clause the client changed with a verdict (red flag, for review, acceptable) and your decision, a positions sheet with the red flags and preferred positions per topic, logs for clarifications, qualifications and notices, and five checks before you price that read the other sheets.
General information, not legal advice. The contract in your pack and your own positions decide the verdicts.