The shared process, and the local rules that decide the outcome. Most of what you know still holds; the traps are where the rules changed.

Herman B. Smith
CEO & Co-Founder
Updated Nov 2, 2026
Denmark runs on EU procurement rules, standard conditions agreed across the industry (AB 18 for construction-only contracts, ABT 18 for design and build) and a specialist complaints board, the Klagenævnet for Udbud.
The guide covers the complaint windows that close before the merits matter, the AB 18 security that runs both ways and the client’s side most bidders forget, who carries the climate-limit risk on new buildings, and the service certificate (serviceattest) that sinks a won bid when ordered too late.
What you will learn in this free guide:
Why the below-threshold works act, in force since 2001, is set to be repealed, and what would replace it from 2027.
The complaint windows that close before the merits ever matter.
How the AB 18 security runs both ways, and the client’s side most bidders forget.
Who carries the risk of the climate limits for new buildings, and why they are checked at completion.
The service certificate that sinks a won bid when it is ordered too late.
Patterns, not advice. The wording in your pack is what matters, and your contract advisers should see it.
Danish construction tendering at a glance
Procurement law
Public: Udbudsloven, the Public Procurement Act, with complaints to the Klagenævnet for Udbud, the Complaints Board for Tenders.
Private: No statutory challenge route. The invitation and ordinary contract law govern.
Public award process
A mandatory standstill of 10 calendar days from the day after the award notice is sent. A complaint filed within it automatically suspends the signing.
Forms and amendments
AB 18 for construction-only contracts, ABT 18 for design and build and ABR 18 for advisory services. A deviation applies only where the agreement states clearly and expressly which points deviate.
Security
AB 18 security runs both ways. Contractor: 15% of the contract sum excl. VAT until handover, then 10%. Employer: three months’ average payments, at least 10% of the contract sum. Public authorities and social housing organisations do not provide one, and private clients can agree it away in the special conditions.
Last verified October 2026. Based on the Udbudsloven, the Complaints Board Act, AB 18 and published commentary.