Learn how construction tendering works on bank-funded and FIDIC-based projects, stage by stage, and the six parameters that decide where a bid is won or lost before you ever submit a price.

Herman B. Smith
CEO & Co-Founder
Updated Oct 27, 2026
On bank-funded work the development bank’s rules set the procurement and FIDIC’s Particular Conditions set the price risk.
The guide covers general procurement notices, prequalification and complaint windows, when a best and final offer (BAFO) is allowed, the banks’ quality weighting and joint venture criteria, the 2017 claim deadlines, and what to check before you price: eligibility and debarment, the Base Date, securities and the standstill.
What you will learn in this free guide:
How tendering works on bank-funded and FIDIC-based projects, from qualification through to award.
How general procurement notices, procurement plans and prequalification shape how bank-funded work reaches the market.
How the development banks’ procurement rules, quality weighting, joint venture criteria and complaint windows affect your bid.
How the FIDIC books, the Particular Conditions and the claim deadlines in the 2017 editions can shift risk and affect margin.
What to check before you price, including eligibility and debarment, the Base Date, securities and the standstill.
Patterns, not advice. The wording in your pack is what matters, and your contract advisers should see it.
Bank-funded and FIDIC tendering at a glance
Procurement rules
Bank-funded: the development bank’s procurement rules set the process. On World Bank-financed work a standstill of 10 business days follows the Notification of Intention to Award, and complaints must be made within it.
Government: national procurement law and its complaint route.
Private: usually no standstill and no one to complain to. The client’s instructions and local law are the rulebook.
Forms and amendments
FIDIC Red, Yellow and Silver Books, 2017 editions, amended through the Particular Conditions. The World Bank and ADB build their construction-only documents on the 2017 Red Book, while contracts on the banks’ 2010 Pink Book still run largely on 1999 numbering.
Notice and time bars
FIDIC 2017 Sub-Clause 20.2: a Notice of Claim within 28 days of becoming aware, or when you should have become aware, of the event, and a fully detailed claim within 84 days or as agreed. Missing a deadline can bar the claim. Check the Particular Conditions, which can change the periods.
Last verified October 2026. Based on the World Bank Procurement Regulations, FIDIC 2017 and published commentary.