Learn how construction tendering works in Sweden, stage by stage, and the six parameters that decide where a bid is won or lost before you ever submit a price.

Herman B. Smith
CEO & Co-Founder
Updated Nov 2, 2026
Sweden’s distinctive layer is AMA (Allmän material- och arbetsbeskrivning): reference books that set standard materials and workmanship under numbered codes.
Tender documents cite the codes instead of writing out requirements, so much of the scope sits in AMA, not the pack. The administrative provisions (administrativa föreskrifter, AF) set the contract terms and decide whether a change to the standard conditions counts: AB 04 for construction-only contracts, ABT 06 for design and build. The guide also covers notice databases, frameworks and private invitations, the Public Procurement Act (LOU) and court review, and what to check before you price: bid validity, written change orders, security and the standstill before signing.
What you will learn in this free guide:
How tendering works in Sweden, from qualification through to award.
How registered notice databases, framework agreements and private invitations shape how work reaches the market.
How Swedish procurement rules, staff register requirements and court review of awards affect your bid.
How AB 04, ABT 06, AMA codes and the inspection regime can shift risk and affect margin.
What to check before you price, including bid validity, written change orders, security and the standstill period.
Patterns, not advice. The wording in your pack is what matters, and your contract advisers should see it.
Swedish construction tendering at a glance
Procurement law
Public: The Public Procurement Act (LOU), for contracting authorities: state and municipal authorities and bodies governed by public law, including most municipal companies.
Private: Governed by the invitation and, in practice, by administrative provisions drafted on the AMA AF template, which bind the process once referenced.
Public award process
A mandatory standstill (avtalsspärr) of at least 10 days from the day after an electronic award notice is sent, and at least 15 days otherwise.
Forms and amendments
AB 04 for construction-only contracts and ABT 06 for design and build. A change to the standard ranks only if it sits in the summary of changes in the administrative provisions (AFC.111 under AB 04, AFD.111 under ABT 06). Successors, AB 25 and ABPU 25, are expected in 2027; until then AB 04 and ABT 06 govern.
Last verified October 2026. Based on LOU, Swedish court rulings, Konkurrensverket guidance and published commentary on AB 04.