Dutch construction tendering at a glance

Procurement law

Public: Aanbestedingswet 2012, for contracting authorities: the State, provinces, municipalities, water authorities and bodies governed by public law.
Private: The invitation and ordinary contract law govern, unless the client is a contracting authority.

Public award process

Notices on TenderNed. A standstill of at least 20 calendar days from the day after the award decision. Only interim court proceedings filed within it stop the signing.

Forms and amendments

UAV 2012 (version 2025) for construction-only works, and UAV-GC 2025 (replacing UAV-GC 2005) for integrated contracts, where the contractor also takes on design, and sometimes maintenance.
Public: Contracting authorities must apply them in full and may deviate only with reasons.

Last verified October 2026. Based on the Aanbestedingswet 2012, the UAV and UAV-GC texts and published commentary.